The installation and debugging of the automatic stereo library project of an electrical enterprise in Wuhan has been completed
- Categories:Engineering Case
- Author:
- Origin:
- Time of issue:2023-01-12
- Views:0
(Summary description)Dingli Intelligence has more than 10 years of practical experience in the industry, according to the actual needs of different enterprise users, can add AGV fault alarm, complex road section traffic control, system remote upgrade and maintenance and other functions, as well as the efficient use of collaborative WMS, fully realize intelligent storage management, and build a one-stop solution combining software and hardware.
The installation and debugging of the automatic stereo library project of an electrical enterprise in Wuhan has been completed
(Summary description)Dingli Intelligence has more than 10 years of practical experience in the industry, according to the actual needs of different enterprise users, can add AGV fault alarm, complex road section traffic control, system remote upgrade and maintenance and other functions, as well as the efficient use of collaborative WMS, fully realize intelligent storage management, and build a one-stop solution combining software and hardware.
- Categories:Engineering Case
- Author:
- Origin:
- Time of issue:2023-01-12
- Views:0
On December 21,2021, Wuhan an electric enterprise automation stereo library project installation and debugging is completed, the project contains 11321, six roadway 2 sets of circular shuttle system and 5 sets of automatic shuttle car system and 1 set of trunk system, 2 sets of mechanical hand palentizing system, can cooperate to complete finished box automatic transportation, palletizing, wrapping film and the whole dish storage operations. At the same time, WCS integrated monitoring system supports the connection with WMS system. Due to the site limitation of the project, there are many uncertain factors, such as the difficult lifting of stacker, the increase of electrical debugging and the chain connection of third-party equipment, which bring a lot of difficulties to the promotion of the project.
However, in the face of difficulties, our project team members withstood the pressure, overcame all difficulties, and actively solved the problems. In order to ensure the progress of the project, the project team entered the site on the basis of the local epidemic prevention and control. After more than a month of overtime on equipment installation, hardware and software debugging, the shuttle car system and elevated warehouse project was finally successfully delivered to the owner for use, which greatly relieved the inventory pressure of the owner and was fully recognized by the owner.
Dingli Intelligence has more than 10 years of practical experience in the industry, according to the actual needs of different enterprise users, can add AGV fault alarm, complex road section traffic control, system remote upgrade and maintenance and other functions, as well as the efficient use of collaborative WMS, fully realize intelligent storage management, and build a one-stop solution combining software and hardware.
Scan the QR code to read on your phone
More cases
Dingli and a furniture enterprise in Jiangmen to cooperate with the automatic three-dimensional warehouse project
Dingli and a furniture enterprise in Jiangmen to cooperate with the automatic three-dimensional warehouse project
Project name: Automatic three-dimensional database case of a pharmaceutical enterprise in Hunan province
020-82002201
TEL:
18102581498
Address: Youbao Industrial Park, No.17 Xiangshan Middle Road, Science City, Huangpu District, Guangzhou
COPYRIGHT © 2020 Guangzhou Dingli Storage Equipment Co., Ltd. ALL RIGHTS RESERVED. 粤ICP备18086819号 Chinese(中文版)